Package 1: Current Status
|
|
Package 1: Introduce & Current Status (December 2011) | E-LNG | 35 | Project Duration | M. Ajami | Project Manager | 973.5 Million Euros | Contract Cost | Power Plant - Continuing installation of Gas Unit 4 - Continuing installation of Gas Unit 5 - Continuing installation of Units 1 & 2, heat recovery Overall progress: 75%
Sea Water Intake - Finalizing bar bending, form working and concrete pouring of the internal walls - Continuing wall backfilling - Continuing concrete pouring of the roof - Starting pile driving for Gantry Crane Overall progress: 76%
Water Utility - Continuing execution of northern and northeastern concrete pipe racks of unit 64 - Continuing the installation of storage tanks - Continuing construction of Rator in unit 62 - Continuing construction of unit 62 substation - Continuing pile driving on unit 67
Overall progress: 26%
| Current Status | UTILITIES & OFFSITE | 24 Months | Project Duration | M. Jannesari | Project Manager | 51 Billion Tomans & 25 Million Euros | Contract Cost | - Continuing execution of roads and canals - Continuing execution of retaining wall - Final stages of executing the administrative buildings structure Overall progress: 38.32% | Current Status | SWEETENING | 29 Months | Project Duration | A. Damircheli | Project Manager | 300 Billion Tomans & 150 Million Euros | Contract Cost | - Continuing execution of pipe rack foundations - Continuing equipment construction - Receiving the second part of equipments on site | Current Status | LIQUEFACTION | 36 Months | Project Duration | Hamid Saffari PhD | Project Manager | 683 Million Euros | Contract Cost | - Conducting the second part of HAZOP - Continuing construction of special heat exchangers - Preparing O.P. for ordering other items - Receiving necessary equipments and parts | Current Status |
|
|
|