Iran LNG
  Sun, February 05, 2012  
 
 Package 1: Current Status 
Package 1: Introduce & Current Status (December 2011)
E-LNG
35
Project Duration
M. Ajami
Project Manager
973.5 Million Euros
Contract Cost
  
Power Plant
- Continuing installation of Gas Unit 4
- Continuing installation of Gas Unit 5
- Continuing installation of Units 1 & 2, heat recovery
 
Overall progress: 75%
 
Sea Water Intake
- Finalizing bar bending, form working and concrete pouring of the internal walls 
- Continuing wall backfilling
- Continuing concrete pouring of the roof
- Starting pile driving for Gantry Crane
 
Overall progress: 76%
 
Water Utility
- Continuing execution of northern and northeastern concrete pipe racks of unit 64
- Continuing the installation of storage tanks
- Continuing construction of Rator in unit 62
- Continuing construction of unit 62 substation
- Continuing pile driving on unit 67
 
Overall progress: 26%
  
 
Current Status
UTILITIES & OFFSITE
24 Months
Project Duration
M. Jannesari
Project Manager
51 Billion Tomans & 25 Million Euros
Contract Cost
   
- Continuing execution of roads and canals
- Continuing execution of retaining wall
- Final stages of executing the administrative buildings structure
 
Overall progress: 38.32%
 
 
Current Status
SWEETENING
29 Months
Project Duration
A. Damircheli
Project Manager
300 Billion Tomans & 150 Million Euros
Contract Cost
 

- Continuing execution of pipe rack foundations

- Continuing equipment construction

- Receiving the second part of equipments on site

 

Overall progress: 49.30%

 
Current Status
LIQUEFACTION
36 Months
Project Duration
Hamid Saffari PhD
Project Manager
683 Million Euros
Contract Cost
 

- Conducting the second part of HAZOP

- Continuing construction of special heat exchangers

- Preparing O.P. for ordering other items

- Receiving necessary equipments and parts

Overall progress: 25.76%
 
Current Status
 
 

 

Powered By RadCom