 Package 3: Current Status  
Package 3: Introduce & Current Status (August 2012)
HARBOUR & JETTIES
23 Months
Project Duration
H. Khanalizadeh
Project Manager
150 Billion Tomans
Contract Cost
 

- Constructing LNG and LPG trestle with 40% progress

- Continuing the installation of core, filter and armour on the main breakwater, wstern and eastern dike

- Pile driving on LNG trestle

 
Overall progress: 85.45%
    
Current Status
  

 