Package 3: Current Status
|
|
Package 3: Introduce & Current Status (December 2011) | HARBOUR & JETTIES | 23 Months | Project Duration | H. Khanalizadeh | Project Manager | 150 Billion Tomans | Contract Cost | - Continuing the installation of core, filter and armour on the main breakwater - Continuing the installation of core, filter and armour on the eastern dike - Continuing the installation of core, filter and armour on the western dike - Pile driving on the LNG trestle Overall progress: 80.59%