 Package 3: Current Status  
Package 3: Introduce & Current Status (December 2011)
HARBOUR & JETTIES
23 Months
Project Duration
H. Khanalizadeh
Project Manager
150 Billion Tomans
Contract Cost
 
- Continuing the installation of core, filter and armour on the main breakwater
- Continuing the installation of core, filter and armour on the eastern dike
- Continuing the installation of core, filter and armour on the western dike
- Pile driving on the LNG trestle
  
Overall progress: 80.59%
 
Current Status
 

 